US data center delays: 10 GW and power equipment orders

US data center delays could postpone orders for transformers, switchgear, and other electrical equipment, but the development restrictions reported in November 2026 do not establish that manufacturers have lost those orders. At least 10 gigawatts (GW) of planned data center capacity face development restrictions across the country, according to a November 17 Financial Times report. The financial impact on equipment suppliers will depend on which projects proceed, what has already been ordered, and when customers take delivery.
For investors following AI infrastructure stocks, the distinction affects earnings forecasts. A postponed purchase order reduces expected new bookings for the affected period. A postponed shipment can move revenue into a later quarter even when the equipment remains in the supplier’s backlog. An outright cancellation creates a different risk because the supplier may lose part of the expected business.
What does the 10 GW figure actually measure?
The Financial Times and regulatory research firm Regbase identified proposed facilities exposed to restrictions using local planning records, public statements, and hearings. The report also identified three Amazon projects in Ohio facing restrictions, with an estimated $17 billion in planned spending and approximately 1.8 GW of expected electricity demand.
The figures describe different aspects of the development pipeline.
| Reported figure | Scope | What it represents |
|---|---|---|
| At least 10 GW | United States | Proposed data center capacity affected by restrictions |
| About $17 billion | Three Amazon projects in Ohio | Planned investment excluding chips and other internal equipment |
| About 1.8 GW | Same three Ohio projects | Expected electricity demand |
| More than $23 billion | AWS investment in Ohio through 2030 | Broader announced investment program |
Ohio’s governor announced the broader Amazon Web Services (AWS) investment program in December 2024. Its scope includes investments beyond the three projects identified in the November 2026 report. Subtracting $17 billion from the broader figure would therefore produce a misleading estimate of the investment still expected to go ahead.
The 10 GW estimate measures proposed capacity exposed to development restrictions, not confirmed canceled capacity. It cannot be converted directly into a dollar amount of lost transformer sales. Each site has its own electrical design, construction phases, procurement arrangements, and grid connection requirements.
Why Amazon’s Ohio projects face uncertainty
On November 3, 2026, voters in Trenton, Ohio, approved Issue 17, a city charter amendment restricting new data center construction above a 25-megawatt (MW) power threshold. Ballotpedia reported preliminary results of 3,541 votes in favor and 903 against, or 79.68% support. Those results apply to Trenton, not to Ohio as a whole.
The dispute involves a development known as Project Mila, which local reporting puts at a planned 250 MW. Prologis, the developer, argues that the project’s earlier zoning and building approvals protect its right to continue construction. Residents supporting the restriction dispute whether the project has acquired those legal protections.
A federal lawsuit filed on November 12 is challenging the application of the amendment to the development. On November 19, local public radio reported that residents had asked to participate in the case to defend the restriction. A final ruling on the project’s right to proceed was not identified in the materials reviewed through November 25.
This case illustrates why data center delays can arise even after construction activity has started. A project may have received permits and committed money to site preparation while its future development rights remain contested. The commercial consequences depend on the scope of the eventual decision and the contracts already in place.
How data center delays affect equipment orders
A large data center needs equipment to receive electricity from a utility or another power source and distribute it safely throughout the facility. Power transformers change voltage levels, while switchgear controls and protects electrical circuits. Distribution transformers and related equipment help deliver electricity at the levels required inside the campus.
Equipment purchases do not all occur when construction begins. Some buyers reserve manufacturing capacity well ahead of installation, especially when delivery schedules are measured in years. Reuters reported in July 2026 that shortages had extended delivery times for certain high-voltage transformers to several years, encouraging utilities and developers to place orders early.
That procurement pattern creates several possible outcomes when development schedules change.
| Project or contract status | Potential supplier impact |
|---|---|
| Equipment has not been ordered | New bookings may shift to a later period. |
| Firm order remains in place | Backlog may be retained despite construction delays. |
| Customer reschedules delivery | Revenue and cash collection may shift, depending on contract terms. |
| Customer cancels or reduces the order | Backlog and expected revenue may fall, subject to contractual protections. |
| Development moves to another location | Existing equipment may be reused, or different specifications may require new orders. |
The effect of data center delays on any particular supplier requires evidence of its involvement in the affected project. Even a confirmed cancellation of a data center would not establish the value of lost equipment sales without information about purchasing commitments and cancellation terms.
Why a growing backlog does not rule out future risk
Eaton Corporation (NYSE: ETN) provides a useful example of how to interpret supplier earnings. Its Electrical Americas segment reported a backlog of approximately $15.99 billion at September 30, 2026, up from $12.01 billion a year earlier. That represents a 33% increase, according to its third-quarter results.
Backlog represents outstanding business that has not yet been recognized as sales, subject to the company’s reporting definition. It gives investors some visibility into future activity, although it does not guarantee that every order will become revenue on the original schedule. Eaton’s September reporting date also precedes the November restrictions.
When assessing whether project delays are affecting earnings, quarterly sales alone offer limited insight. A manufacturer may continue delivering equipment ordered in earlier periods even as customers slow new purchasing. Conversely, new orders can remain strong while shipments are postponed and reported sales temporarily weaken.
A useful measure is the book-to-bill ratio, calculated by dividing new order value by sales or billings over the same period, using the company’s definition. A ratio above 1 indicates that new business exceeds the amount delivered or billed under that measure. Investors should also check cancellation disclosures and changes in expected shipment timing, since those can affect backlog independently of new bookings.
Which electrical equipment companies have US exposure?
The effects of data center delays could extend beyond US-listed manufacturers because South Korean suppliers serve the North American electrical infrastructure market. Their business exposure differs by product type and customer base, so a common industry headline does not establish an identical earnings risk for each company.
Hyosung Heavy Industries
Hyosung Heavy Industries has disclosed US contracts covering 765-kilovolt (kV) transmission equipment, including extra-high-voltage transformers. Its exposure includes large-scale grid infrastructure investment, which serves data centers as well as other electricity customers.
HD Hyundai Electric
HD Hyundai Electric operates a power transformer manufacturing business in Alabama. Its US production facilities give the company direct exposure to domestic demand for electrical infrastructure. Changes in utility investment schedules and transformer delivery commitments are relevant to its future earnings.
LS ELECTRIC
LS ELECTRIC has announced North American data center supply agreements involving switchgear and distribution transformers. These products are closely connected to the electrical distribution systems installed within large computing facilities.
The companies’ disclosures establish commercial activity in the relevant market. They do not establish that any of these suppliers has a contract for the three affected Amazon projects. Equipment purchased by a utility for broader grid expansion can also serve customers other than data centers.
Investors can further distinguish equipment supply contracts from agreements to provide electricity or reserve generating capacity. The Talen Energy capacity deal illustrates how a power producer can earn contracted revenue through capacity commitments. Equipment manufacturers generally face a different set of delivery, production, and payment obligations.
What investors should monitor next
To assess the financial effect of data center delays, follow the project and the equipment supplier separately. Project-level developments include court decisions, revised construction schedules, utility connection agreements, and changes in planned capacity. Supplier disclosures can then show whether those developments have translated into changes in order intake, delivery schedules, or revenue expectations.
The following indicators address different aspects of earnings risk.
| Indicator | What it helps establish |
|---|---|
| New orders | Whether customers continue to purchase equipment |
| Order backlog | Whether outstanding business is growing or shrinking |
| Contract cancellations | Whether previously expected sales have been lost |
| Delivery schedules | Whether revenue is shifting between reporting periods |
| Revenue and margin guidance | Whether management expects a financial impact |
| Factory utilization | Whether slower demand is affecting production efficiency |
The distinction also matters for stock valuations. If deliveries slip while firm contracts remain intact, near-term earnings estimates may change without an equivalent reduction in total expected contract revenue. Repeated cancellations, lower replacement orders, or unused factory capacity could create a more persistent earnings problem.
There is no confirmed link in the reviewed disclosures between the three Ohio projects and canceled equipment orders at the manufacturers discussed here. The investment case for AI-related electrical equipment therefore still needs to account for actual bookings, contractual commitments, and shipment schedules. Those disclosures offer a firmer basis for evaluating earnings risk than the headline capacity figure alone.
Information reviewed through November 25, 2026.
Source:
- Financial Times — Amazon’s $17bn Ohio AI data centre bet threatened by voter backlash
- Ohio Governor’s Office — Governor DeWine Announces $10 Billion Investment Plan from Amazon Web Services in Greater Ohio
- Ballotpedia — Trenton, Ohio, Issue 17, Prohibit Data Centers Initiative
- WCPO — Prologis Sues Trenton Over Voter-Approved Data Center Restrictions
- WOSU Public Media — Trenton Residents Intervene to Protect Voter-Approved Data Center Ban
- Justia — Trenton Data Center Campus LLC v. City of Trenton
- Reuters — US Power Companies Scramble to Secure Equipment as Surging Data Center Demand Strains Supplies
- Eaton — Third Quarter 2026 Earnings Results
- FinancialFilings — Eaton Corporation Quarterly Report for September 30, 2026
- Hyosung — Hyosung Heavy Industries to Supply 765kV Transmission Grid as a Full Package to the US
- HD Hyundai Electric — US Operations and Manufacturing Facilities
- LS ELECTRIC — North American Data Center Power Infrastructure Solutions